Categories

JAVA DATEBASE
Technology Network Community
Oracle Database
Fusion Middleware
Development Tools
Java
Desktop
Server & Storage Systems
Enterprise Management
Berkeley DB Family
Cloud Computing
Big Data
Business Intelligence
Architecture
Migration and Modernization
E-Business Suite
Siebel
PeopleSoft Enterprise
JD Edwards World
Industries
JD Edwards EnterpriseOne
User Productivity Kit Pro (UPK) and Tutor
Governance, Risk & Compliance (GRC)
Master Data Management (MDM)
Oracle CRM On Demand
On Demand: SaaS and Managed Applications
AutoVue Enterprise Visualization
Primavera
ATG
Agile PLM
Endeca Experience Management
Fusion Applications
Archived Forums

 



Tags

Primavera P6 Enterprise Project Portfolio Management


Create Overlapping Financial Period


Hi,  my question is that ;      - actual values to be stored,  change based on the update period (I've monthly, weekly updated projects)     - "store period performance" work with financial periods      - for same time span monthly and weekly financial periods cannot be created. Error message says "The financial period timescale overlaps with an existing financial period.  The financial period was not added."   what is the solution ? How I can create these financial periods or any other way to store actuals ?  thanks for replies ,  hatice

Overlapping financial periods is not currently possible.  There is an outstanding enhancement request for this functionality to be added so I would contact Oracle and add yourself to:  "Is there a way to put in overlapping financial periods? [ID 900334.1]"  Only alternative I can think of is to create a separate database for weekly vs monthly financial periods. Maybe someone else has a more creative solution.

I just confirmed this is still not possible in the newest release P6r82.  While not pretty another possibility may be to create monthly Financial Periods in the current year and weekly Financial periods in a past previous year (ie: 1980).


Related Links

Role Teams and Resource Teams in P6 Web do not show rolled up summary
Resource assignment to Parallel activities
activities dates from "status" started and finished; to their relationships
When will the Excel Utilities (SDK) [ID 895537.1] Be Available for P6 8.2?
BI Publisher: UDF title in column header
Primavera P6 R8.2 SSO integration with SiteMinder
BI Publisher does not see new projects
How to define Revenue of a Project in Primavera P6
Export Templates Steps in P6
UCM Configuration with P6
Calculating Remain Finish Date/ Remain Start Date
64 bit install
Application Exception when running a report
Clear oracle database 10g xe
Remove/Hide Summary Bar in P6V8.2 Web application
Statusing email schedule everyday